Raghuganga Hydropower Limited | Location : Myagdi District | Generation : 40 MW | Annual Average Energy : 247.89 GWh | Turbine Type : Pelton ( Vertical Axis)

visitnepal2020
  • Phone Number
  • 069-521017

Progress Status of RGHPL

Progress Status of RGHPL

Progress Status of RGHPL

PROJECT PROGRESS STATUS UP TO CHAITRA

1.1Project Develop Milestone.

S.no

Date

Milestone

1

2075/12/18

Power Purchasing Agreement with NEA.

2

2068/8/1

Forest and Public Area land Reclamation obtained

3

2068/8/28

Approval of Tress Cutting Obtained.

3

2074/8/5

Lot 1 agreement with Jay Prakash Associates.

4

2075/12/20

Access Road Completed.

  1. Generation license for the project were received from Ministry of Energy Water Resources and Irrigation for a period of 30 Years.
  2. Approval for cutting down trees was obtained from Department of forestry. Trees cutting has been completed as of now.
  3. Land Acquisitions and encroaching is completed.
  1. Preparatory of Project Works: Access Roads (10.87 Km)
    1. The access road leading to different project components site has been completed.
    2. Slope protection, widening of road (Gabion wall), grading and other finishing works is almost completed.
    3. Construction of Side drain is ongoing.
    4. Foundation of Steel through Truss Bridge is on process which connects Mauwaphat to Headworks.
  2. Camp Facilities

    The construction of camp facilities consisting of following building has been completed:

    1. 2 nos. of Residential Building Type D.
    2. 4 nos. of Residential Building Type C.
    3. 1 nos. of Guard House.

    Remaining 5 Different types of Buildings and other recreational purpose (Badminton and Basketball Court) are in under constructions.

  3. Progress of work under main Packages:

    Package 1(Civil and Hydro-Mechanical works)

    Contract agreement for Lot 1- Civil and Hydro-Mechanical Works of Raghughat Hydroelectric Projects was signed with Jay Prakash Associates. Major activities progress status under this contract are as:

    • ADIT Tunnel
      1. Access roads to Adit tunnels has been completed.
      1. Portal face mapping at Adit-2 and Adit-3 has been done.
      2. Survey layout and center line alignment of Adit-2 and Adit-3 has been checked prior to ribs installation.
      3. Shuttering work and subsequent concreting viz, portal column (M25) and backfill concreting (M15) was carried out as per approved design drawings.
      4. Ribs installation as well as laggings placement was done as per the technical specification provided.

     

     7.Transmission

 

    1. Extension and Strengthening of 11KV line from Power House to ADIT 3, Batching Plant, Crusher APP and Surge Shaft is completed.
    1. Extension and Strengthening of 11 KV line for Headwork’s, ADIT 2 is initiated.        

 

        8 .Surge Shaft

    1. Site Clearance for Surge Shaft is completed. 
    1. Excavation work is ongoing.
  • Power House
    1. Site Clearance for Power House is completed.
    1. Landscaping and Slope Stabilization is going on.
    2. Crusher Plant (Aggregate Processing plant) and testing laboratory is installed and initiated.
    3. Batching plant is installed and commissioned.

Package 2(Electro-Mechanical works).

Contract for Lot 2- Electro-Mechanical Works has been completed Tender and Evaluation of Tenderer for Technical Specification is on process.

 

SUMMARY

The Monthly Progress Report is prepared for providing the successive information regarding the project status till date. Over all 12% work has been completed.

 

  1.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                               

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                                 Fig:- Gabion work