PROJECT PROGRESS STATUS UP TO CHAITRA
1.1Project Develop Milestone.
S.no |
Date |
Milestone |
1 |
2075/12/18 |
Power Purchasing Agreement with NEA. |
2 |
2068/8/1 |
Forest and Public Area land Reclamation obtained |
3 |
2068/8/28 |
Approval of Tress Cutting Obtained. |
3 |
2074/8/5 |
Lot 1 agreement with Jay Prakash Associates. |
4 |
2075/12/20 |
Access Road Completed. |
Camp Facilities
The construction of camp facilities consisting of following building has been completed:
Remaining 5 Different types of Buildings and other recreational purpose (Badminton and Basketball Court) are in under constructions.
Progress of work under main Packages:
Package 1(Civil and Hydro-Mechanical works)
Contract agreement for Lot 1- Civil and Hydro-Mechanical Works of Raghughat Hydroelectric Projects was signed with Jay Prakash Associates. Major activities progress status under this contract are as:
7.Transmission
8 .Surge Shaft
Package 2(Electro-Mechanical works).
Contract for Lot 2- Electro-Mechanical Works has been completed Tender and Evaluation of Tenderer for Technical Specification is on process.
SUMMARY
The Monthly Progress Report is prepared for providing the successive information regarding the project status till date. Over all 12% work has been completed.
Fig:- Gabion work